Segmental Groined Dome




Segmental groined dome completed in 5 days with 4 masons


Segmental groined dome used for the cost effective house
This segmental groined dome has been built free spanning to cover the kitchen/living room of a cost effective house in Auroville. This groined dome has been generated by the intersection of two segmental vaults.

The segmental groined dome has been in 5 days with an average of 4 masons. The segmental groined dome and vault presents these features:
•    Segmental section of 3.48 m span and 50 cm rise
•    Total vaulted roof length: 13 m
•    Thickness of the vault and dome: 7 cm


CONSTRUCTION SEQUENCES


Starting the side vaults


Building the side vaults


Fixing the steel template and starting the groined dome

Building the segmental groined dome

Segmental groined dome near completion

Segmental groined dome completed in 5 days

CONSTRUCTION DETAILS

Building the segmental vault on the window frame as a template


Building the segmental vault by steps to start with


Building the segmental vault above the bedroom


Completing the vault and controlling the shape with a straight edge

Finishing the side vault


Starting the segmental groined dome

Building the segmental groined dome


Adjusting a block in the corner of the groin


Building the segmental groined dome with 4 masons


Laying blocks in the corner


Segmental groined dome in progress

Laying blocks


Completing the groined dome

Finishing the dome with 1 mason

Groined dome towards completion



 